• M/s. Bharat Mumbai Container Terminals Pvt. Ltd. (PSA) was awarded the development of Fourth Container Terminal on a DBFOT basis through a Concession Agreement on 6th May, 2014.
• The project comprises of two phases – each phase comprises 1 Km of quay line, dredging of maneuvering area, 12 quay cranes, 46 RTG Yard cranes, and 4 RMGC cranes for its rail yard generating capacity of 2.4 Million TEUs each (total 4.8 MTEU). The cost of Phase I is ₹ 4719 Crs and estimated cost of Phase -II is ₹ 3196 Crs.
• As per schedule, the work of Phase I was completed on 22nd December, 2017 and put into operation with a capacity of 30 MTPA.
• Amendment in Environmental and CRZ Clearance for revised layout received on 18th October, 2021.
• The Phase II works commenced on 17th April, 2022 after fulfillment of condition precedent and expected commissioning by April, 2025.
• Increase the overall Port handling capacity to more than 10 Million TEUs
• Reinforces JNPA’s position as the premier container port of India
Phase I was put into operation on 22nd December, 2017. Phase II Work commenced On 17th April, 2022.
JNPA has established a multi-product port based Special Economic Zone (SEZ), in line with the objective of port-led industrialization, of Sagarmala vision, under the Ministry of Port, Shipping and Waterways’. This SEZ is strategically located and boasts excellent connectivity via waterways, airways and roadways, making it an ideal hub for export-oriented industries in India. The port has made significant investments in state-of-art infrastructure to support the industries. JNPA is the developer and the Special Planning Authority for the SEZ, having its own Development Control and Promotion Regulations (DCPR), sanctioned by the Government of Maharashtra.
Key features enhancing the ease of doing business include a streamlined Single Window Clearance approval mechanism for essential services such as building permits, electricity, water, and fire safety. Moreover, JNPA SEZ has obtained all necessary clearances and permissions, including Environmental Clearance from the Government of India (GoI), Consent-to-Establish and Consent-to-Operate from the Maharashtra Pollution Control Board (MPCB), and an Electricity Distribution License from the Maharashtra Electricity Regulatory Commission (MERC).
The SEZ's attractiveness is further bolstered by its proximity to critical infrastructure projects, including the Mumbai Trans Harbour Link (MTHL), Suburban rail to Uran, Dedicated Freight Corridor (DFC) rail corridor and upcoming transport infrastructure like Navi Mumbai International Airport and Virar-Alibaug Multi-Modal Corridor. These connections position JNPA SEZ as a premier manufacturing destination, aiming to set new benchmarks in port-led industrialization in India.
The SEZ covers a total land area of 277.38 hectares (685 acres), with approximately 163 hectares (403 acres) available as leasable land. The SEZ is operational from June 24, 2020. The SEZ allots plots for a 60-year lease period through E-Tender cum E-auction.
As of now, 54 plots have been issued LOI comprising 307 Acres of land, with 9 units and 1 Free Trade Warehousing Zone (FTWZ) already in operation. Other Units/ Co-developers are in different stages of development like awaiting approvals or operational documentation process. The operational units are engaged in diverse sectors such as warehousing, food processing, manufacturing, and trading.
Conceptually, a MMLP is a terminal situated in the hinterland servicing a region connected with one or several ports by rail and/or road transport and is offering specialized services between the MMLP and the overseas destinations. Normally the MMLP is container-oriented and s\upplies all logistics facilities including various Value addition opportunities, which are needed for shipping and forwarding agents in a port. The MMLP is situated in Sindi village, Wardha district of Maharashtra and is proposed to be constructed over an area of 140 hectares in a phased development, by SPV of JNPA and NHAI (NHLML).
The planned ICD cum industrial park encompasses the various components of an envisioned successful multimodal logistics park. Concepts, such as the defined and planned above, in conjunction with a focus on the right regulatory and institutional support are the way forward to reduce logistics costs and help build a robust logistics sector in India. This will aid in the development of systems and networks that will address the issues of underdeveloped material handling infrastructure and inefficient modal mix.
MoU between JNPT and NHAI was executed for MMLP on 22.10.2021. As per the provisions of MoU, the SPV has been formed and the further development of MMLP project will be executed by NHAI/NHLML being a lead member of SPV. The MMLP will be monitored by NHLML.M/s. DC Multimodal Park Pvt. Ltd. is selected as operator By NHAI.
Conceptually, an MMLP is a terminal situated in the hinterland servicing a region connected with one or several ports by rail and/or road transport and is offering specialised services between the Dry Port and the overseas destinations. Normally the MMLP is container-oriented and supplies all logistics facilities including various Value addition opportunities, which are needed for shipping and forwarding agents in a port. The MMLP is situated in Jalna near the Aurangabad district of Maharashtra and is proposed to be constructed over an area of 182 hectares in a phased development, by SPV of JNPA and NHAI (NHLML).
The presence of industrial regions with existing and upcoming enterprises helps establish synergies between the industry and its logistic requirement and create an efficient network that shall enable reduced logistics to cost; improved freight aggregation, distribution, storage; and ensure a faster delivery to customers. Thus, the proposed dry cum industrial park has the potential to evolve as a model for other such similar Multimodal logistics parks. At the same time, the development of a concept entails the right combination of essential components such as transport connectivity, industrial park facilities, information technology systems, and policy / regulatory reforms.
-Operation of Maintenance contract was Awarded to M/s. Container Corporation of India Ltd. for a period of 09 years. LOA issued on 12-03-2024.
-EPC model for the development of balance facilities: - Bids for construction of balance facilities like balance work of external connecting road, Warehouse, Admin and customs office, Container yard, Steel scrap yard, fencing etc. The work is awarded on 30.07.2024 to M/s. JPR Balaji Infra Pvt. Ltd. The 12% work is completed.
Land for Dry Port is available at Niphad Sugar factory and other storage facilities. The Land value is examined by the District Collector and (Administrator of Sugar Factory).
The planned ICD cum industrial park encompasses the various components of an envisioned successful multimodal logistics park. Concepts, such as the defined and planned above, in conjunction with a focus on the right regulatory and institutional support are the way forward to reduce logistics costs and help build a robust logistics sector in India. This will aid in the development of systems and networks that will address the issues of underdeveloped material handling infrastructure and inefficient modal mix
Description:
The scale of operations of JNPA have increased over the last decade and there is a need for accommodation for various Government Agencies and Private Agencies as well as Commercial organizations in order to accommodate them in the Port area. In the recent past, various meetings were held with stakeholders under the ‘Ease of Doing Business’ and it is ascertained that there is a need for accommodation for various categories of organizations.
In this regard, JNPA has decided to establish a business facilitation center in JNPA to accommodate the Port Users and also provide office space for the trade. These office premises shall be developed with green and smart technology building concept with innovative techniques including facilities to optimize energy, performance, innovation in design within Port Estate. The building near the existing PUB building shall be developed as Business facilitation center having area of 4767 sqm. to accommodate the Government and semi Govt. offices (PGA’s).
The facility to be created under the subject scheme is as follows:
A) BUSINESS FACILITATION CENTRE (near port users building):
i. Accommodation for Partner Government Agency offices related to Port activities.
ii. Office premises for Commercial organizations like Banks, Financing Companies, etc.
iii. National Accredited Laboratories.
iv. Space for Port Users Offices
v. Cafeteria and Parking
vi. Auditorium
B) PORT FACILITATION CENTRE (Inside Port area)
i) Offices for CISF and Marine Department
ii) Facilities for seafarers
iii) Accommodation for Port pilots and VTS operators
iv) Office for immigration, Cafeteria for Port visitors.
iv) Conference Rooms and Parking.
Benefits of the Project:
Facilities for seafarers, PGA’s, Banks, Finance Companies, Port Users in one roof and office space for JNPA’s Marine, CISF Department including accommodation for pilots.
Status:
The work is in progress.
Description:
The JNPA has developed SEZ on 277.38 Ha Area; SEZ has become operational since 24th June 2023. In order to give direct access to the JNPA SEZ, a grade separator is being constructed on SH 54 to ease the movement of the traffic towards JNPA SEZ and port. Hence, in order to give direct access, a grade separator construction work is initiated by JNPA and the structural part (erection of girders, deck slab and RCC crash barrier) above SH 54 are already constructed on the 80 m span. Two RCC retaining walls of 20 meters each on both the sides of both the approaches are constructed. The reinforced earth walls are constructed up to 6-meter height on both side approaches. Further the bridge under the present contract has to be constructed between the RE walls i.e. 190 meter SEZ side and 210 meter on Railway side.
Benefits of the Project:
To ease the movement of the traffic towards JNPA SEZ and port & Seamless entry / exit to the JNPA SEZ project.
Status:
The work order has been issued to the contractor M/s JMMIPL-PDIPL JV on 16.01.2024 and the intended completion date for the whole of the work is 30th Mar. 2026. As this work is highly technical, the PMC M/s Aakar Abhinav Consultants (I) Pvt. Ltd. is also appointed to assist the JNPA to complete the RCC bridge. The work is in progress.
Description:
Jawaharlal Nehru Port Authority, to cater to the additional volume of liquid cargo and to address the issues of congestion and vessel waiting time at the Port has constructed Additional Liquid Cargo Berth (LB-3 and LB-4) with a capacity of 4.5 MTPA through EPC mode. The works of “Equipping, Operation, Maintenance and Transfer of Additional Liquid Cargo Berths LB3 and LB4 at JN Port” has been awarded to M/s. JSW Infrastructure Limited through PPP route.
Expected Date of Completion - April 2026
Sanctioned/Projected Cost (In Crores)- Rs. 68.87
Expected Cost (In case cost overrun) (In Crores) – NA
Physical Progress (%) -
Financial Progress (%) fulfillment of condition precedent.
Benefits of the Project:
Status:
Award of Concession has been issued on 22nd August, 2024. Custom custodianship obtained by the concessionaire on 24.10.2024. The concessionaire shall fully operationalize the jetty within 18 months i.e. by February 2026.
Description:
The work of Distribution of water supply line from Gavan Phata to Port area in connection with 40 MLD water supply scheme is in progress through Maharashtra Jeevan Pradhikaran (MJP) on full deposit scheme.
Benefits of the Project:
Additional Water Supply Storage capacity in existing Infrastructure.
Status:
The work is in progress.
Description:
The estimate for the secondary division works out to Rs. 16,14,70,000/- (Including GST, Contingencies and Press Advertisement Charges). The estimated quantities are based on the structural audit and survey report which are accessed by the structural auditor and estimated rates are based on the SSR 20-21, market rates & DSR 2018-19 (for electrical items).
Benefits of the Project:
To maintain the structure & increase life of structures.
Status:
The work is in progress. Physical progress – 60% Financial progress – 50%.
Description:
M/s. Indian Port Rail & Ropeway Corporation Ltd. is carrying out this rail connectivity project between Jasai and JNPA for the 4th container terminal of JNPA on behalf of JNPA.
Benefits of the Project:
Creation of Port Rail Connectivity Infrastructure.
Status:
Project is on the verge of completion.
The proposed entrance gate building is expected to serve as an important entry and facility point for JNPA employees, port users, visitors, national and international dignitaries, VIP’s etc. Thus, connecting the city and the sea through the terminal building.
The proposed passenger terminal building at the landing jetty is planned and conceptualized as a gateway to JNPA from the sea side. It is proposed to be developed as part of an image building and branding initiative of JNPA. This is in addition to its function as a passenger terminal.
The space requirements for the Entrance Gate Building at Landing Jetty are kept in view of the current as well as future requirement of daily commuters. As per the data on passenger traffic (last six months) gathered from marine department, currently on an average 500 passengers travel daily to and fro from the jetty. Apart from JNPA, CISF employees and locals, the facility is also used by port users, agents, contractors, customs employees etc. In future, with the development of areas in JNPA such as SEZ, Non-SEZ industrial area, township redevelopment, 12.5% R&R scheme, tourism activities etc. the footfall is expected to increase in future with expected increase in water transport.
The foreign delegates, VIPs also use waterways to reach JNPA from Mumbai. The building has a provision of a VIP waiting room with facilities.
Ease of doing business & port development.
The Competent Authority approved to award work on 11th September, 2024.