1:
Redevelopment of Bulk Terminal into Container
Terminal
Due to dwindling of Dry Bulk cargo traffic, the Port
has decided to redevelop its existing Bulk Terminal
into Container Terminal on BOT basis. The total
Quay length of the terminal is 712 mtr. Total
capacity of the terminal is estimated to be 1.3
million TEUs (15.6 million Tones). Estimated cost of
the project is Rs.900 crores.
License Agreement between JNPT and Gateway
Terminals India Pvt. Ltd. was signed on 10.08.2004.
The Licencee has commenced the work of demolition of
sheds. The Terminal is likely to be in operation by
August 2006.
2:
Extension of
Container berth and other facilities at JN Port
In view of expected growth in container traffic,
faster turnaround time, accommodating larger size
container vessels, optimum utilization of feasible
water front area and avoiding difficulties in
container staking, Port is planning to extend
Container berth by 330 m and other facilities with
extension of guide bund by about 160 m at on
orientation of 10° clockwise with respect to the
alignment of existing guide bund. The area of about
27 hectares is required to be reclaimed for
container stacking and the development of other
facilities. This also includes construction of
Finger Jetty of about 50 m length. The estimated
cost of the project is Rs.453/- crs. and it is
likely to be in operation by 2008. It is assumed
capacity addition of about 7.2 million Tones (ie 0.6
million TEUs) per annum.
The Port has carried out model studies through CWPRS
to explore the feasibility to extend the container
berths along with reclamation at the North. The
Port has also approached MOEF in November 2004 for
obtaining environmental clearance for the project.
The modalities of execution of this project need to
be worked out.
3:
Development of
Fourth Container and Marine Chemical Terminal
It is envisaged from various studies that the port
would be required to handle the Container traffic to
the tune of 6.8 Million TEUs in year 2015-16. In
order to handle the traffic after re-development of
Bulk Terminal into Container Terminal, further
terminal facility will be required. In view of
this, Port is planning to develop fourth container
terminal as an extension of BPCL jetty and Chemical
Terminal, on BOT basis. The salient features of the
project are as under.
Phase-I:
Phase-I development includes construction of
additional 700 m of container quay line with
conversion of existing 300 m of liquid cargo berth
into container so as to make 1000 m for handling
containers and chemical terminal of 600 m quay line
for handling A, B, C class liquid cargo along with
200 hectares of land to be reclaimed. Existing 300
m Liquid cargo facilities will be shifted to
Chemical terminal. It includes reclamation of 200
hectares of land, development of 100 hectares of
land for yards, dredging, road and rail
connectivity, etc. Construction of berths and
acquisition of equipments will be made on BOT
basis. It is estimated that the container handling
capacity is 26.4 million Tonnes (ie 2.2 million TEUs)
and liquid handling capacity is 6 million Tonnes.
The estimated cost of Phase-I development is
Rs.2567/- crs. It is likely to be in operation by
2009-10.
Phase-II:
Phase-II development includes construction of
additional 1000 m of container quay line for
handling containers, chemical terminal of 600 m quay
line for handling A, B, C class liquid cargo. It includes
development of 100 hectares of land for yards ,
dredging, road and rail connectivity, etc.,
Construction of berths and acquisition of equipments
will be made on BOT basis. It is estimated that
container handling capacity is 26.4 million Tonnes (ie
2.2 million TEUs) and liquid handling capacity is 9
million Tonnes. The estimated cost of Phase-II
development is Rs.2134/- crs. It is likely to be in
operation by 2013-14.
The Port has decided to conduct feasibility studies
for this project. The consultancy work is awarded to
M/s Consulting Engineers Services. The consultant
have submitted Inception report. The Feasibility
report is expected to ready by October 2005.
4:
Deepening & widening
of main harbour channel and JN Port channel
At present, large size vessels having draught of
12.5 mtrs, navigate through Mumbai Harbour Channel
and JNP Channel, making use of tidal window.
Availability of sufficient draught in the port is
very necessary for optimum utilization of capacity
and faster turn around of larger vessels. With
increasing trend towards larger size container
vessels, draught would become an important factor in
the choice of port by the shipping lines which are
thinking of deploying larger size vessels to achieve
economies of scale. In order to accommodate larger
size container vessels, Port is planning to deepen
and widen existing Main Harbour channel and JN Port
approach channel. The channel can be dredged in two
phases. The salient features are as under
|
Sr. No |
Description |
Phase-I |
Phase-II |
|
1 |
Channel can be dredged for |
accommodating container vessel of capacity
6000 TEUs & upto 14 m draught by making use
of tidal window |
accommodating container vessel of capacity
6000 TEUs & upto 14 m draught at all states
and 9000 TEUs & upto 15 m draught by making
use of tidal window |
|
2 |
Maintained depth at the Channel entrance |
13.9 m below CD |
16.1 m below CD |
|
3 |
Maintained depth at JNP channel |
12.8 m below CD |
15.0 m below CD |
|
4 |
Width of channel |
370 m for straight reach. 450 m at bends
and in front of JNP berths |
About 370 m for straight reach. 450 m at
bends and in front of JNP berths |
|
5 |
Length |
33.55 Km |
About 38 Km |
|
6 |
Estimated Cost of the project |
Rs.800 crores |
Rs.1150 crores |
|
7 |
Likely completion |
November 2008 |
After 2012 |
Environmental Clearance from MOEF for Phase-I was
obtained in March 2004. Phase-I work
is at tender stage. Phase-II work is at planning
stage.
5:
Port's Rail
connectivity from Panvel to Port
JN Port is connected to the national network of
Railways through Panvel-Uran Section of Central
Railway. Panvel is further connected to Konkan
Railway, Diva on Central Railway and Vasai on
Western Railway. Port is presently handling about
12-14 trains per day each way which may likely to go
upto 18 trains per day each way. To handle
increased number of trains, Central Railway has
taken up the work doubling of existing railway track
from Panvel to Port. The salient features are as
under.
Phase-I:
Doubling of rail line from Panvel to Port has been
taken up by the Railway Authority. The work is in
progress by Railway Authority and same is likely to
be completed by May 2006.
The
Port has conducted Rail Transport logistic studies
through M/s RITES for long term perspective on rail
and road corridors serving the port and identifying
measures that would need to be taken to decongest,
augment or expand these systems. They have
submitted the final report
6.
Improvement of
Port’s road connectivity –
At present port is connected through two lane
National Highway (NH-4B) to Mumbai-Pune Express Way,
Mumbai-Goa Highway (NH-17) and through two lane
State Highway (SH-54) to Navi Mumbai, Thane, Nasik,
Ahmedabad. To meet future requirements of
increasing container traffic, Port has decided to
improve the road connectivity by forming Special
Purpose Vehicle (SPV) between JNPT, NHAI and CIDCO.
Salient features are as under.
Phase – I:
National Highway Authority of India (NHAI) have
already taken up the work for widening of National
Highway (NH-4B) about 26 Km from 2 lanes to 4
lanes. The work is completed. The work of
widening of State Highway (SH-54) and Amra Marg
about 16.5 Km is in progress. The cost of the
project is Rs.357 crs and JNPT's contribution in the
form of equity and sub-ordinate debt is Rs.100 crs.
The Port is also planning to develop two grade
separators in the form of Flyover Bridge ie; one at
Karal junction and another is at Gavhan junction for
efficient movement of traffic. The estimated cost
of the project is Rs. 125.00 crs. It is assumed that
the work will be executed through existing SPV. Feasibility studies for these
arrangement are under scrutiny by NHAI.
Phase –II:
The following projects have been considered.
i)
Widening of NH 4B from four lane to six lane about
26 Km.
ii) Development of second link to Port starting
from Container Freight Station (CFS) and running
along side the creek to connect Amra marg at Ulva ie;
about 10.5 Km.
iii) Widening / strengthening of road connectivity
to NH-17 from Khopta to Sai ie.; about 16 Km.
7:
Improvement of
Internal Port Roads:
Due to increased container traffic, Port internal
road connectivity is required to be improved. Port
has planned to widen its existing Port roads from
four lanes to six lanes which also include
development of parking areas at various locations.
In order to improve the internal road connectivity
of the Port, various phase wise schemes have been
identified in the form of immediate, short term and
long term proposals for implementation as per the
feasibility report prepared by M/s TPA consultancy
services. Estimated cost of the Immediate and
short term proposals is about Rs.55 /- crs.
The various immediate development works are in
progress.
8:
Deployment of
additional machineries, equipments and Port crafts
Acquisition of 20 Nos. RTYGCs, 4 Nos RMQC, 3 Nos of
RMGC, 20 Nos of TT, Tugs and Pilot Launches, safety
equipments, and Container Terminal Computer Center (CTCC)
will be done phase wise and as per the
requirements. 08 RTGCs are procured and 4 new
RTGCs are acquired replacing the old one. 20 nos. of TT
are already acquired. Work order is placed for
procurement of 02Nos of RMGCs and same will be
commissioned in June 2006. Procurement of 03
Nos of RMQCs are at tender stage.
9:
Development of Back up Facilities:
Port has prepared Land Use Plan on the basis of
future traffic projections. Port has planned to
develop back up area for port operational activities
such as warehouses, Container Freight Station (CFS),
Tank Farms, Cold storages, Export/Import yard,
Ancillary facilities and Utilities etc.
It is planned to develop phase wise infrastructure
facilities such as roads, sewerages,
electrification, water supply, ancillary facilities
and utilities etc. in the back up area. The
estimated cost of the project is Rs.510/- crs. The phase
wise developments are at planning stage.