Widening of National
Highway from 2 lanes to 4 lanes.
Widening of State highway & Amra Marg: from 2 lane
4 lane.
Total cost: Rs.3570 millions.
Undertaken by SPV between JNPT, CIDCO & NHAI.
JNP's Contribution: Rs.1000 millions.
Work is in progress and may complete by 2005-06
Click on
the image to enlarge
Rail
Connectivity - Phase - I
Doubling of existing Rail track from Port to Panvel is
under consideration by Railways with estimated cost of
Rs.600 millions.
Commencement: 2003-04 & completion by 2005-06.